How far has Nagpur Metro Phase 2 progressed?
Phase 2 adds about 43 km to Nagpur Metro. By mid-2026 roughly 35 to 40% of its civil work was reported complete, and Maha Metro moved to the first track-laying contract, worth about ₹216.5 crore, covering two corridors of about 24 km with 15 stations.
| Corridor (track contract) | Length | Stations |
|---|---|---|
| Reach 1B: NCI station to MIDC ESR | 17.5 km | 8 |
| Reach 3A: Lokmanyanagar to Hingna | 6.5 km | 7 |
| Total in this contract | about 24 km | 15 |
Why does this matter for Samruddhi Circle?
- Reach 1B starts at the National Cancer Institute (NCI) station; NCI is about 5 minutes from Godrej Rivershore Estate (Google Maps, approximate).
- It extends the Orange Line axis towards the MIDC industrial area on the south side, linking homes on the south-west with jobs.
- Reach 3A extends the Aqua Line towards Hingna, on the west side where New Nagpur is planned.
- Today the Nagpur Metro station is about 10 minutes from the project.
When will Phase 2 open?
No firm opening date was given with the track-laying contract. Earlier estimates pointed to 2028 to 2029. Treat any date as a target until stations open. Metro and MIHAN outlook.
Travel times from Godrej Rivershore Estate are approximate, per Google Maps, and change with traffic.
Frequently asked questions
What is the status of Nagpur Metro Phase 2 in 2026?
About 35 to 40% of civil work was reported complete by mid-2026, and a ₹216.5 crore track-laying contract covers NCI to MIDC ESR and Lokmanyanagar to Hingna.
Which Nagpur Metro Phase 2 station is near Samruddhi Circle?
The Phase 2 corridor towards MIDC ESR starts at the National Cancer Institute station; NCI is about 5 minutes from Godrej Rivershore Estate.
How long is Nagpur Metro Phase 2?
About 43 km in total.